How to Find and Close an Open or Expired Permit in Unincorporated Miami-Dade
An open or expired permit can surface when you sell, refinance or apply for a new permit. If your property is in unincorporated Miami-Dade, the county handles your permit records, not a city. This guide walks through who issues permits, how to look up your property’s permits on the county’s system, what the statuses mean, and the usual paths to close or reactivate a permit. Every case is different, and approval always rests with the building department.
Who issues permits in unincorporated Miami-Dade?
Miami-Dade County’s building department, part of the county’s Department of Regulatory and Economic Resources, issues permits for properties in unincorporated Miami-Dade. The county explains that its permit process applies only to properties whose folio number starts with “30.” Each city in Miami-Dade has its own building official who issues permits inside that city’s limits. If you’re not sure which one applies to you, the county suggests checking with the Property Appraiser to see which municipality your property is in.
The county’s permitting office is the Herbert S. Saffir Permitting and Inspection Center, 11805 SW 26 Street, Miami. The main number is 786-315-2000, and the Permit Section can be reached at 786-315-2100.
How to look up permits on the county portal
Miami-Dade County lets you search permit records online for free through its Building Permit Selection Menu. Here’s a simple way to use it:
- Open the Building Permit Selection Menu on the county’s e-Permitting site.
- Start with your address or folio. Use “Process/Permit Number Cross-Reference (Address)” to list permits tied to your address. Enter the street address only, in the county’s format (for example, “11805 SW 26 ST,” with no city, state or ZIP).
- Check for open permits. Choose “Open Master Permits (Address)” or “Open Permits by Folio (Folio Number)” to see permits that haven’t been closed.
- Open each permit number. Use “Permit History Inquiry” and “Permit Inspection History” to see what was issued and which inspections passed.
- Look for anything holding the permit up. “Permit Outstanding Requirements” and “Permit Inspection Holds” show what the county still needs before it can move forward.
- Check for code cases too. The county’s Building Support Case Search covers building code enforcement cases in unincorporated Miami-Dade, and the Neighborhood Code Case Search covers neighborhood code violations.
Write down every permit number, its type (building, electrical, plumbing, mechanical, roofing) and the last inspection on file. That list becomes your closeout plan.
What “open,” “expired” and “final” mean
- Open: A permit was issued, but not all required inspections have been approved, so it hasn’t been closed out.
- Expired: The permit ran out of time. Miami-Dade County says that once a permit is issued, you have 180 days to complete the work and call for inspections. An approved inspection on the master permit or any sub-permit extends the permit for another 180 days from the approval date. If that window passes with no approved inspection, the permit can expire.
- Final: All required final inspections have been approved. The county advises getting proof that all final inspections were approved, or a Certificate of Completion or Occupancy, before making a final payment to a contractor.
Typical steps to close or reactivate a permit
The right path depends on what your records show and what was actually built.
1. The work was done and the permit is still active. Schedule the missing inspections. The county says to schedule one business day before the day you want the inspection, before 4 p.m., Monday through Friday. You can schedule online, through the automated system at 305-591-7966, or by contacting the Permit Counter at 786-315-2100. On inspection day, the county’s Routes & Results page shows the inspector’s information and your place in the queue.
2. The permit expired before the work was finished or inspected. The county’s Portal has a “Permit Reissuance” option to reissue an expired permit, and the county asks for the approved plans to be included. The same Portal also has “Permit Extension” and “Change of Contractor” options if those fit your situation better.
3. No work was ever done. The county has a Request for Expired Permit Check form, which must be signed and notarized by the owner or contractor. The form notes that open or expired permits issued before 1998 require an expired permit check inspection. If a newer permit already covered the same scope of work, the form says to use a Request for Permit Cancellation instead and pick the “Superseded by Another Permit” option.
4. Work was done without a permit. If something was built or changed with no permit at all, a new permit application covering that existing work is usually needed. The building department decides what documents, plans and inspections it will ask for, so get those requirements in writing before you start.
To confirm that all inspection approvals are on file, the county says you can call the Permit Records Section at 786-315-2100.
Owner-builder notes
Miami-Dade County allows owner-builder permits in unincorporated areas, with limits:
- You may build or improve a one-family or two-family home, or a farm outbuilding, for your own use or occupancy. It can’t be built or improved for sale or lease unless a licensed contractor listed on the permit completed the project.
- The property must be in a person’s name, not a company or trust.
- For commercial property, the county limits owner-builders to a one-story building or addition of no more than 500 square feet, or maintenance and repairs of no more than $5,000.
- After your application and plans are approved, you schedule an owner-builder validation with the county’s Small Business and Homeowner Permitting Assistance Team, in person or virtually. The permit is issued only after you pass it. You’ll need a valid photo ID and proof that the property is your primary residence.
- If a home you built or substantially improved is sold or leased within 24 months of the permit being issued, the law presumes it was done for sale or lease.
If you take over an old permit as an owner-builder, you take on the legal responsibility for that work.
Free South Florida Owner-Builder & Contractor Permit Checklist
Get our free checklist: what to gather and the steps to follow before you apply.
FAQ
How do I know if my property is in unincorporated Miami-Dade?
Miami-Dade County says its permit process applies to properties with folio numbers that start with “30.” You can also check with the Property Appraiser to see which municipality, if any, your property is in.
Can I search Miami-Dade County permits online?
Yes. The county’s Building Permit Selection Menu lets you search by address, permit number, process number or folio, including options for open master permits and open permits by folio.
How long is a Miami-Dade County permit good for?
The county gives you 180 days after a permit is issued to complete the work and call for inspections. An approved inspection on the master permit or a sub-permit extends it another 180 days from the approval date.
Can an expired permit be reissued?
Yes. The county’s Portal has a “Permit Reissuance” option for expired permits, and the approved plans need to be submitted with it. The building department reviews and decides each request.
What if the permit was pulled but the work never happened?
The county’s Request for Expired Permit Check form covers that, and it must be signed and notarized. Permits issued before 1998 require an expired permit check inspection.