Demolition Permits in South Florida
Demolition is not automatically permit-exempt because you are removing something rather than building it. Miami-Dade’s building guidance requires permits for interior renovations such as knocking down a wall, and its demolition requirements distinguish total demolition from removing a structure attached to a residence. Environmental review can be part of the process too. Before opening walls or taking down a structure, describe the complete project to the building department serving the address. Ask which demolition, renovation, trade and environmental approvals apply. A contractor’s description of a job as “interior demo” does not decide its permit requirements.
Is interior demolition different from a teardown?
Yes, and the application should make that difference clear. Removing finishes, removing partitions, removing part of a building and demolishing a detached structure are different scopes. Miami-Dade’s permit guidance identifies knocking down a wall and altering electrical or plumbing systems as work that needs permits. Its demolition checklist separately addresses detached structures and structures attached to the main residence.
Tell the department what will remain as well as what will be removed. If demolition is part of a larger remodel, ask whether the removal belongs within the renovation permit or requires its own application. Do not assume a separate demolition permit is required in every city for every interior project. The city’s building department decides how to classify the proposed work.
Which building department do I contact?
For unincorporated Miami-Dade, begin with the County building department. Within a municipality, contact the city’s department. Broward’s Building Code Division provides permitting in the Broward Municipal Services District and areas served under contract; other municipalities have their own arrangements.
Our guide to the issuing department helps you identify the right office. Existing records can provide useful context: see the City of Miami guide or unincorporated Miami-Dade guide, depending on the address. A mailing address alone should not be your only jurisdiction check.
What information should the application show?
Miami-Dade’s demolition requirements ask for an application identifying the structure and its area. For attached demolition, its checklist calls for detailed drawings, including a site plan showing the location, electrical and plumbing connections to be removed, and applicable calculations.
As a practical preparation list, gather:
- The address, folio and available existing permit records.
- Photographs and a description of the area to be removed.
- A plan distinguishing remaining construction from demolition.
- The location of affected electrical and plumbing connections.
- The proposed work that follows the demolition, if any.
- Environmental review documents requested for the property and project.
For commercial demolition of an attached structure, Miami-Dade requires the drawings to be signed and sealed by an architect or engineer. Ask the department which drawings need professional preparation for your project and which trade applications are required. Miami-Dade notes that subsidiary electrical and plumbing permits may be necessary after the demolition permit is issued. Removing a building component does not eliminate the need to address its connections safely through the required process.
Does asbestos review apply?
Check this before disturbing materials. Miami-Dade’s RER asbestos guidance says most commercial demolition and renovation projects, and certain residential facilities, require asbestos review and approval. Its residential examples include buildings with five or more units, multiple small residential buildings on the same property, and residential demolition that forms part of a larger development project.
The County’s asbestos page says an asbestos survey must be completed for all demolition projects, and for renovation projects where more than 160 square feet of suspect friable asbestos-containing materials and Category I and Category II nonfriable materials will be disturbed. For a regulated demolition or asbestos renovation, the Notice of Demolition or Asbestos Renovation must be filed with RER in advance of the start date, within the notice period the County sets. Confirm that requirement before scheduling the work. Ask RER which requirements apply to the actual building, materials and scope. Do not assume that a small residential address is automatically outside every asbestos-related requirement, or that a building permit replaces environmental review.
Broward has its own Asbestos Compliance Program. Under Section 27-180 of Broward’s air quality code, projects subject to the asbestos regulations must submit, in advance of the work, a Statement of Responsibilities Regarding Asbestos, a Notice of Demolition or Asbestos Renovation and a thorough asbestos survey. Confirm the required submissions directly with the County program and the local building department.
This guide does not provide material-testing or removal instructions. The appropriate project professionals and reviewing agencies should determine what evaluation and handling are required.
Can an asbestos affidavit replace a survey?
Miami-Dade expressly says its Affidavit for Asbestos Survey does not replace the survey. The form may allow renovation plan review to proceed while the survey is being arranged, but the underlying requirement remains. Have the project team explain which document serves which purpose.
Keep environmental documents with the building application. If the removal scope changes, ask whether the environmental review also needs updating. A document describing one affected area should not be assumed to cover additional demolition elsewhere in the building.
What if demolition is proposed to help resolve a violation?
Removing unpermitted work is still work to discuss with the building department. Miami-Dade’s enforcement guidance says bringing a property into compliance may involve permits, required work, inspections and addressing unsafe conditions. Ask the official handling the case whether the proposed removal is an acceptable compliance route and what evidence is needed afterward.
See our violation notice guide and code violation services page. Keep the enforcement case number separate from the permit number. Ask both offices what remains outstanding rather than assuming one approval completes everything.
Frequently asked questions
Do I need a permit to remove an interior wall?
Miami-Dade lists knocking down a wall among interior renovations that require permits. Confirm the permit classification and drawing requirements with the building department serving your property.
Does every interior demolition need a separate demolition permit?
Do not assume that it does. Describe the removal and any related remodel to your city’s building department and ask whether the work is included in a renovation permit or needs a separate application.
Can electrical or plumbing permits be needed for demolition?
Yes. Miami-Dade’s demolition guidance says subsidiary electrical and plumbing permits may be required. Show the connections affected by the proposed removal.
Does a building permit replace asbestos review?
No. Miami-Dade and Broward have environmental requirements for projects subject to asbestos regulations. Ask the applicable County program what documentation your project needs.
Does Miami-Dade’s asbestos affidavit replace the survey?
No. Miami-Dade states that its Affidavit for Asbestos Survey does not replace the asbestos survey. Confirm the survey and submission requirements with RER.
Talk through your project
Permit Busters is a South Florida permit expeditor. We help owners, contractors and real estate agents line up demolition permits, coordinate the environmental paperwork and close out demolition permits once the work is done. Bring the property address, the demolition scope and any violation notice. Approval always rests with the government.
Call (954) 616-5823 to talk through your project.
This page is general information, not legal advice. Rules vary by city and county and can change. The building department with jurisdiction makes every permit decision, so confirm current requirements with that office.