Direct answer

A Florida building permit stays active only if you follow the expiration and inspection rules that apply to that file. For a single-family dwelling, Florida law says a local building permit expires one year after it is issued or on the effective date of the next edition of the Florida Building Code, whichever is later, unless the local government extends it. Many departments also require inspections within a shorter period stated on the permit card. Know those dates, schedule inspections when the work is ready, and apply for an extension before the file expires.

Disclaimer

This article is general information about permitting and code-enforcement processes. It is not legal advice, not a substitute for advice from a Florida-licensed attorney, and not a guarantee of any result, timeline, or fee. Permit Busters, LLC is not a law firm and does not appear as your legal representative. Building and code rules vary by county and municipality and can change. Confirm current requirements, forms, and fees with the building or code office that has jurisdiction over the property, and consult a Florida attorney and, where construction work is required, a Florida-licensed contractor.

Este artículo es información general sobre procesos de permisos y cumplimiento del código. No es asesoramiento legal, no sustituye el consejo de un abogado con licencia en Florida y no garantiza un resultado, un plazo ni un costo. Permit Busters, LLC no es un bufete de abogados y no comparece como su representante legal. Las normas de construcción y de código varían según el condado y el municipio y pueden cambiar. Confirme los requisitos, formularios y tarifas vigentes con la oficina de construcción o de código que tenga jurisdicción sobre la propiedad, y consulte a un abogado de Florida y, cuando se requiera obra, a un contratista con licencia en Florida.

The statewide rule for single-family permits

Florida Statutes section 553.79(1)(c) has three parts that owners and contractors should know:

  • A local government that issues building permits may send a written notice of expiration, by email or United States mail, to the owner and the contractor listed on the permit, no less than 30 days before the permit is set to expire. The notice must identify the permit and the expiration date. The word “may” matters. Do not assume a reminder will arrive.
  • A building permit issued by a local government for a single-family dwelling expires one year after issuance or on the effective date of the next edition of the Florida Building Code, whichever is later.
  • The same paragraph says this does not prevent a local government from extending a building permit beyond the expiration date.

The Florida Building Code also has a progress rule used by many departments: a permit can become invalid if work does not start within six months after issuance, or if work is suspended or abandoned for six months. Work is generally treated as in active progress when the permit has received an approved inspection within 180 days. Your permit card and the issuing department’s current procedures control any local variation. Confirm those dates with that department.

If your project is not a single-family dwelling, ask the issuing department for the expiration rule that applies to that occupancy.

A new application filed after a new edition of the Florida Building Code takes effect is reviewed under the new code.

Local inspection clocks still matter

The statute is not the only clock on the file. The issuing department can have commencement and inspection rules of its own, and those rules appear on the permit card, in the department’s procedures, or both.

Miami-Dade County’s published guidance for unincorporated permits is a clear example. The County’s how-to-apply page says that once a permit is issued you have 180 days to complete the work and call for inspections, and that an approved inspection on the master permit or any sub-permit extends the permit for another 180 days from the approval date. The County’s homeowner permit FAQ states the same clock this way: an issued permit is valid for 180 days and can expire if the work does not start, or if an approved inspection does not occur, within 180 days. That FAQ wording matches the Florida Building Code progress rule used statewide: a permit can become invalid if work is not commenced within six months after issuance or if work is suspended or abandoned for six months, and work is considered in active progress when the permit has received an approved inspection within 180 days. In practical terms, keep approved inspections current; you do not necessarily have to finish the entire job in 180 days. The County also lets applicants request a permit extension or a reissue of an expired permit through its submission portal, and it accepts process-number extension requests by email to RER-SPA@miamidade.gov, with a letter signed by the property owner, the design professional, or the contractor on record.

Other departments use their own wording. Palm Beach County PZB publishes separate fees to renew or extend a permit, depending on how long the file has been inactive. Broward cities publish their own expired-permit procedures; Fort Lauderdale lists Expired Permit Procedures and an Expired Permit Renewal Request Form on its Development Services documents page. Always use the issuing department’s current rule.

If you are not sure which department issued the permit, read Which Department Issues Your South Florida Permit.

Steps that keep a permit active

  1. Read the permit card the day it is issued. Note the issue date, any printed expiration date, the required inspections, and any holds, such as a Notice of Commencement.
  2. Put the inspection dates on a calendar. Do not wait until the work is “almost done” to learn that a foundation, roof dry-in, or rough-in inspection had to be called first.
  3. Schedule inspections only when the work is ready. A failed inspection does not always start a new expiration period. An approved inspection is what many departments, including unincorporated Miami-Dade, use to extend the file.
  4. Keep the approved plans on site. Miami-Dade requires stamped, approved plans at inspections and tells permit holders that approved documents are available through its portal for a limited time. Other departments have the same expectation even if their retrieval window differs.
  5. Ask about an extension before the file lapses. If the job is delayed by weather, materials, a change in contractor, or a redesign, file the extension or renewal the department provides, rather than letting the permit expire and then applying to reissue it.
  6. If the contractor changes, tell the department. A change-of-contractor application is often required before the new contractor can call inspections. Florida law also allows a later contractor to complete the conditions of a permit and obtain inspections, and limits that contractor’s responsibility to the work he or she performs.

If the permit has already expired

An expired permit is not a dead end, but it is a different process. Florida Statutes section 553.79(16) allows a current owner to close a permit, and it allows an expired permit that is substantially complete, as determined by the local enforcement agency, to be closed without a new permit in the circumstances the statute describes. A local agency may also close a permit six years after issuance if it finds no apparent safety hazards. For the local steps, see How to Close an Expired Permit in Broward County and How to Close an Expired Permit in Palm Beach County, and the permit closeout service page.

Do not keep working on an expired permit as if it were still in force. If you are unsure of the status, search the department’s portal or call the permit records desk.

Related pages: residential permits, commercial permits, City of Miami, Fort Lauderdale, and Boca Raton.

Get help keeping a permit on track

Permit Busters, LLC helps property owners and contractors read permit conditions, request extensions or reissue reviews, and prepare closeout documents when a file has already lapsed, in Miami-Dade, Broward, and Palm Beach. We discuss fees and scope before work starts. Our fees are non-refundable once work begins. Government fees are separate, and we accept all types of payment options.

Call (954) 616-5823, email info@permitbusters.com, or book an appointment. You can also text 305-906-0810. We are in Lauderhill, FL 33351. Hours are Monday through Friday, 9 AM to 5 PM.

FAQ

Is there a time limit on permit applications and permits?
Yes. For unincorporated Miami-Dade, the County says permit applications and issued permits are valid for 180 days unless work starts or an approved inspection occurs within that period, and it publishes a process for extensions. Other departments use their own clocks. Florida law also sets a one-year or next-code-edition expiration for single-family dwelling permits unless the local government extends them.

How long are building permits good?
It depends on the issuing department and the type of permit. Florida Statutes section 553.79(1)(c) says a local building permit for a single-family dwelling expires one year after issuance or on the effective date of the next edition of the Florida Building Code, whichever is later, unless the local government extends it. Your permit card may also require inspections within a shorter period.

Are permits good for as long as you need, as long as you get the proper inspections along the line?
An approved inspection often extends the department’s inspection clock, but that is not a blank check to keep a permit open indefinitely. Miami-Dade County says an approved inspection on the master permit or a sub-permit extends an unincorporated permit for 180 days from the approval date. The statutory single-family expiration still applies unless the department extends the permit.

What is the easiest way to extend a permit?
Use the issuing department’s extension or renewal process, and file it before the permit expires. In unincorporated Miami-Dade, a permit extension is submitted through the portal, and a process-number extension is requested by a signed letter to RER-SPA@miamidade.gov. Do not assume a plan revision will extend the expiration date; Miami-Dade specifically says a revision will not extend it.

What if I make a change or revision after my permit is issued?
Submit the revision the way the department requires, with any updated plans and fees. Miami-Dade County says a revision is reviewed in the same manner as a new submittal and will not extend the expiration date of the permit. If the job is also running out of time, submit the extension or renewal as a separate request.

Questions about a property? Call Permit Busters at (954) 616-5823.